Search
  • barrhavenward3

August 4th - Barnsdale Road From: Greenbank Road To: Viewbank Road Construction

AUTHORIZATION TO CLOSE STREET FOR THE PURPOSE OF CONSTRUCTION

Under the following conditions:

Duration:

  • Wednesday, 5 August 2020 to Friday, 13 November 2020.

Signage/Conditions:

  • The contractor is to provide a revised TCP.

  • The contractor is to close Barnsdale at Borrisokane restricting access to local traffic only for the duration of the closure.

  • The contractor is to provide a detour using William McEwan, Brophy/Bankfield, Prince of Wales to Greenbank as part of this closure.

  • The contractor is to provide detour signage on Borrisokane Southbound directing commuters to William McEwan.

  • Maintain pedestrian/cyclists access and provide pedestrian/cyclist detours if necessary.

  • Maintain access to adjacent dwellings and businesses at all times. This includes emergency vehicle access.

PVMS Pre-Notification as follows, to be in place 1 week in advance of the closure:

Barnsdale, between Viewbank and Greenbank, facing both Eastbound and Westbound traffic:


PVMS Message 1

PVMS During the Closure:

  • PVMS to be placed approximately 150m West of William McEwan facing eastbound traffic on Barnsdale, approximately 150 m North of Barnsdale on Trail Road facing Southbound traffic and at the intersection of Barnsdale and Borrisokane facing Southbound commuters.

PVMS Message 1

Barnsdale approximately 150m East of Greenbank.


PVMS Message 2

Other:

  • Contact the City's Right of Way Permits Unit; Inspection_Office@Ottawa.ca if the date of closure changes from that stated on the application.

  • At any time during the work, the City Traffic Management Inspector, at his/her discretion, may instruct the contractor to supply and install additional traffic control devices (signs, barrels etc) and/or retain point duty police to control traffic. The contractor is responsible for all costs.